A) Approve Change Order No. 1 to project RFP-12-05 NORTH LEE COUNTY WTP, (NLC WTP), WELLFIELD EXPANSION - PHASE 2B: RAW WATER PIPELINE AND WELL HEAD FACILITIES, to Mitchell & Stark Construction, Inc., Contract No. 6072, in the amount of $221,610.79 with an additional contract time of 105 days. B) Authorize Chair to execute Change Order on behalf of the Board. (#20130260-UTILITIES)
Files
PDF Document  A) Approve Change Order No. 1 to project RFP-12-05 - Blue Sheet.doc
PDF Document  A) Approve Change Order No. 1 to project RFP-12-05 - Change Order No. 1.pdf
PDF Document  A) Approve Change Order No. 1 to project RFP-12-05 - Executed Agreement.pdf
PDF Document  A) Approve Change Order No. 1 to project RFP-12-05 - c13a Executed Docs.pdf